- Project No:
- 9910
- Project Title:
- Erzincan Girlevik 2 and Mercan Hydroelectric Power Plants
- Client:
- IC Ictas Energy Generation & Trade Inc.
- Start - Finish:
- 1999 - 2001
- Venture Type:
- Alone
Detailed Description:
Girlevik II - Mercan HEPP, is the first in Turkey with its property of producing electrical energy by receiving water from two different sources to two different loading pools at different elevations and from loading pools to same power plant by forced pipelines (steel).
Girlevik II HEPP
Installed Power : 2,880 kW (2 x 1,440 kW)
Annual Generation : 12,980,000 kWh
Turbine Type : Francis (horizontal)
Flow : 2 x 2.25 cum/sec
Net Head : 69.30 m
Forced Pipeline : 212 m, 1,200 mm Inner Diameter St 37/2 Steel
Head Pond : 40m x 7m x 7m
Intake Channel : 7,330 m
Step-Up Transformer : 2 x 1,600 kVA
Mercan HEPP
Installed Power : 9,450 kW (2 x 4,725 kW)
Annual Generation : 27,640,000 kWh
Turbine Type : Francis (horizontal)
Flow : 2 x 2.40 cum/sec
Net Head : 216.70 m
Forced Pipeline : 683 m, 1,200 mm Inner Diameter St 37/2 Steel
Head Pond : 46m x 7m x 7m
Intake Channel: 10,028 m
Step-Up Transformer: 2 x 5,220 kVA
Power Plant and Other Facilities
Power Plant (787 sqm)
500 m Spillway Channel
890 m Drainage Channel
3 each Chute Structure
2 each Energy Breaker
1,600 m Connection Road
160 kVA Power Transformer
63 kVA Stand-By Diesel Generator
Services Provided By ESER
Construction Supervision
Commissioning
Start-up Inspections