- Project No:
- Project Title:
- Other Fuel Storage and Distribution Facilities
- Client:
- Start - Finish:
- 1980 - 2010
Detailed Description:
0912 - Erbil Refinery OSBL Facilities Pipelines - IRAQ
(KAR Construction and Engineering, 2009-2010)
Piping Systems Between Erbil Refinery and Tank Farm Detailed Engineering
0808 - TaqTaq Oil Field Crude Oil Flow Lines - IRAQ
(Zozik - Görkem Joint Venture, 2008)
3300 m, 6 inch Crude Oil Flow Lines and Manifold Connection Detailed Enginering
0704 - Konya Main Airforce Base Fuel Pipeline
(Ministry of Defense, 2007-2009)
5560 m, 6 inch Pipeline, Cathodic Protection System, Valve Pit and Fuel Transfer Pumps Detailed Engineering and Construction Supervision
0619 - Mersin Fuel Pier F-76 Pipeline Connection
(Ministry of Defense, 2006)
1600 m, 8 inch F-76 Pipeline From Mersin Tank Farm to Fuel Pier, 10 cum Drainage Tank, 3 each Valve Pit and Cathodic Protection System Detailed Engineering
0616 - Khurmala Oil Field Manifold Stations - IRAQ
(Kar - Avrasya Oil & Gas Services JV, 2006)
Khurmala Oil Field South, Middle and North Areas Choke Valve and ESD Manifold Stations Piping, Structural and Instrumentation Detailed Engineering
0504 - Istanbul Haramidere Fuel Terminal Bunker System
(Petrol Ofisi Inc., 2005)
Preperation of Process and Instrument Diagrams for the Bunker System
0420 - Canakkale Kepez Fuel Terminal Bunker System
(Petrol Ofisi Inc., 2004)
Preperation of Process and Instrument Diagrams for the Bunker System
0409 - Mersin Fuel Pier Restoration
(Ministry of Defense, 2004-2006)
Renewal of Fuel, Fire Water Pipelines, Pipe Racks and Cathodic Protection System of the Existing Fuel Pier Detailed Engineering and Construction Supervision
0406 - Konya Main Airforce Base FOB Facilities Jet Fuel Storage Tanks
(Ministry of Defense, 2004-2006)
Restoration of 3 each 1000 cum Storage Tank and Epoxy Coating, Level Measurement Systems, 2 each Oil/Fuel Seperator System and 1,750 m Wire Fence Detailed Engineering and Construction Supervision
9508 - Kirikkale Fuel Storage Facilities
(Turkuaz Oil Products Inc., 1995)
Environmental Impact Assessment for 2 each 2000 cum, 4 each 1000 cum Fuel Storage Tank, Pump Station and 4 km Pipeline
9502 - Iskenderun - Elazig Fuel Pipelines Route Study
(Ministry of Defense, 1995-1996)
316 km 8 inch Iskenderun-Malatya and 127 km 6 inch Malatya-Elazig Fuel Pipelines Route Study Detailed Engineering
9207 - Elazig - Batman Pipeline Pump Stations Restoration
(Ministry of Defense, 1992)
Renewal of Pump Groups at Elazig - Batman Pipeline Pump Stations Detailed Engineering
9007 - Batman, Bismil, Diyarbakir Pump Stations Renewal of Pump Groups
(Ministry of Defense, 1992)
Renewal of 8 each Main Line Pump Group at 3 Pump Station Basic Engineering
8905 - Iskenderun Fuel Operations Center
(Ministry of Defense, 1989-1990)
Fuel Operations Center Basic Engineering
8902 - Akhisar Airfield F-16 Facilities
(Ministry of Defense, 1989)
Jet Fuel Storage and Dispensing Facility Basic Engineering
8704 - Slice 38 Various Fuel Facilities
(Ministry of Defense, 1987-1989)
Pump Stations, Manifold and Valve Pits Detailed Engineering and Construction Supervision
8002 - Konya Main Airforce Base Jet Fuel Storage Facilities
(Ministry of Defense, 1980-1984)
Jet Fuel Storage Tanks, Manifold, Piping and Truck Loading Station Detailed Engineering and Construction Supervision
0507 - Konya Main Airforce Base Aircraft Parking Apron Fuel Hydrant System
(Ministry of Defense, 2005)
Restoration of Existing Filter / Water Seperator Station, 3 each Prefabric Hydrant Refueling Pit
550 m, PN 16 DN 150 PE Steel Pipe, 550 m, PN 16 DN 200 PE Stainless Steel Pipe, Pipelines Hydrostatic Tests, Pipelines Cathodic Protection System, Provision of PN 16 DN 100 Pantograph on the Aircraft Apron Detailed Engineering
0408 - Erzurum Tank Farm - Ilica Fuel Pipeline
(Ministry of Defense, 2004-2005)
2,500 m, PN 100, DN 150 New Pipeline Construction, 2 each Highway Crossing (114 m)
River Crossing (54 m), Hydrostatic Tests,Cathodic Protection with Transformer/Rectifier System Detailed Engineering and Construction Supervision
9908 - Restoration of Fuel Storage Tanks at Izmir Uzunada Naval Base
(Ministry of Defense, 1999-2000)
Restoration of 2 each 8,350 cum Fuel Storage Tank (41,85 m diameter and 6 m height) at Uzunada Naval Base Detailed Engineering and Construction Supervision
0909 - Dogancay Railway Fuel Pipeline Variant
(Elen Enerji Inc.,2009)
For 6 inch Pipeline (90 bar), 418 m Variant Construction, 30 m Railway Crossing with 10 inch Casing, Hydrostatic Test and Cathodic Protection System Detailed Engineering
0904 - Istanbul Kurtkoy TEM Junction Fuel Pipeline Variant
(Orhan Evin - Kucukel Joint Venture, 2009)
For 6 inch NATO Pipeline 285 m Variant Construction and Cathodic Protection System Detailed Engineering
0901 - Bogacay River Fuel Pipeline Variant
(Ministry of Defense, 2009)
For 8 inch Pipeline (90 bar), 612 m Variant Construction, at 2 Location Total 30 m Road Crossing with 12 inch Casing, Hydrostatic Tests and Cathodic Protection System Detailed Engineering
0816 - Adapazari Mekece Fuel Pipeline Variants
(Firat Construction Ltd., 2008)
1,870 m Variant Construction, Hydrostatic Tests and Cathodic Protection System at 8 Location for 6 inch Pipeline (90 bar) on Ankara-Istanbul High Speed Train Railway Route at Adapazari Mekece Region Detailed Engineering
0804 - Izmit, Uskudar; Bandirma Fuel Storage Tanks Restoration
(Ministry of Defense, 2008)
Renewal of Tank Bottom Steel Plates and Epoxy Coating of the 4 each 1250 cum and 2500 cum Storage Tanks Detailed Engineering and Construction Supervision
0717 - Fuel Pipelines Variants (Year 2005)
(Ministry of Defense, 2007-2008)
For 4,6,8 and 10 inch NATO Pipelines, at 12 Location Total 4025 m Pipeline Variant, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
0711 - Istanbul Samandira Fuel Pipeline Variant
(Bayraktar Kardesler Construction Inc., 2007)
For 6 inch Pipeline (90 bar), 1011 m Variant Construction, 26 m Road Crossing with 10 inch Casing, Hydrostatic Test and Cathodic Protection System Detailed Engineering
0710 - Iskenderun Dortyol Fuel Pipeline Variant
(Atakas Inc., 2007)
For 8 inch Pipeline (90 bar), 1188 m Variant Construction, 36 m Road Crossing with 12 inch Casing, Hydrostatic Test and Cathodic Protection System Detailed Engineering
0709 - Istanbul Samandira Fuel Pipeline Variant
(Ismail Oncel Ltd., 2007)
For 6 inch Pipeline (90 bar), 427 m Variant Construction, Hydrostatic Test and Cathodic Protection System Detailed Engineering
0707 - Malatya Beylerderesi Fuel Pipeline Variant
(State Highways 8th District Directorate, 2007)
For 6 inch Pipeline (90 bar), 5 m Road Crossing with 10 inch Casing, 202 m Variant Construction, Hydrostatic Tests and Cathodic Protection System Detailed Engineering
0706 - Afyon Sandikli State Highway Fuel Pipeline Variants
(Simsekler İnşaat Ltd., 2007)
For 8 inch Pipeline (90 bar), at 4 Location 245 m Road Crossing with 12 inch Casing, at 2 Location 595 m Variant Construction, Hydrostatic Tests and Cathodic Protection System Detailed Engineering
0701 - Istanbul Europe Side Fuel Pipeline Displacement
(MVM Turizm ve Ticaret Ltd., 2007)
6 inch 80 m Pipeline (90 bar) Displacement, 22 m Crossing with 10 inch Casing and Cathodic Protection System Detailed Engineering
0622 - South Antalya Tank Farm Restoration of Storage Tanks
(Ministry of Defense, 2006-2007)
Renewal of Insulations and Epoxy Painting of the 10000 cum and 5000 cum Storage Tanks Detailed Engineering and Construction Supervision
0608 - Antalya - Cukurhisar Pipeline Damages and Fuel Facilities Restoration
(Ministry of Defense, 2006)
8 inch, 530 m Pipeline (90 bar) Renewal, 105 m River Crossing, 40 m Gabion, 1500 m Pipe Insulation and 6200 sqm Roof Restoration at 12 Stations Detailed Engineering and Construction Supervision
0607 - West Turkey Fuel Facilities Restoration
(Ministry of Defense, 2006-2008)
6 each 10 cum Drainage Tank, 8500 sqm Roof Restoration at 20 Station, 380 m Perimeter Fence, Concrete Pavement, Hydrostatic Test and Cathodic Protection System Detailed Engineering and Construction Supervision
0606 - Elazig - Mus Pipeline Damages and Fuel Facilities Restoration
(Ministry of Defense, 2006-2007)
6 inch, 3,325 m Variant Construction (90 bar), 86 m River Crossing, Hydrostatic Test and Cathodic Protection System, 7,500 sqm Paved Areas and Internal Roads Restoration at 3 Stations Detailed Engineering and Construction Supervision
0605 - Malatya - Batman Pipeline Damages and Fuel Facilities Restoration
(Ministry of Defense, 2006)
4 and 6 inch, 790 m Pipeline (90 bar) Renewal, 70 m River Crossing, 120 m Gabion, 2300 m Pipe Insulation, 3600 m Wire Fence at 5 Stations and 4300 sqm Roof Restoration at 11 Stations Detailed Engineering and Construction Supervision
0501 - Istanbul Formula 1 Access Road Fuel Pipelines Variants
(Kucukel Construction Ltd., 2005)
6 inch 130 m Pipeline (90 bar) Displacement, 85 m TEM Motorway Crossing with 10 inch Casing, 16 inch 122 m BOTAS Natural Gas Pipeline Displacement, 96 m TEM Motorway Crossing with 20 inch Casing and Cathodic Protection System Detailed Engineering
0418 - Izmit Mercedes Benz Factory Fuel Pipeline Variant
(Mercedes Benz Turk Inc., 2004-2005)
6 inch 322 m Pipeline (90 bar) Variant Inside Factory Area, 178 m Paved Area Crossing with 10 inch Casing, Hydrostatic Test and Cathodic Protection System Detailed Engineering and Construction Supervision
0302 - Fuel Pipelines Washout Damages (Year 2001)
(Ministry of Defense, 2003-2005)
or 4,6,8 and 10 inch Pipelines (90 bar), 654 m River Crossing, 3700 m Variant Construction, 160 m Railway and Road Crossing, 113 m Gabion Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
0202 - Tersakan River Fuel Pipeline Variant and Various POL Facilities Restoration
(Ministry of Defense, 2002-2004)
For 6 inch Pipeline (90 bar) 80 m Variant Construction, at 6 Tank Farm Concrete Pavement and Internal Road Construction Detailed Engineering and Construction Supervision
0004 - Restoration of Fuel Facilities at East Turkey
(Ministry of Defense, 2000-2002)
Detailed Engineering and Construction Supervision for Various Restoration Works at 15 Tank Farm
0003 - Restoration of Fuel Facilities at West Turkey
(Ministry of Defense, 2000-2002)
Detailed Engineering and Construction Supervision for Various Restoration Works at 13 Tank Farm
0002 - East and West Anatolia Fuel Pipeline Variants (Year 1999)
(Ministry of Defense, 2000-2002)
For 4,6 and 8 inch Pipelines (90 bar), 2990 m Variant Construction, 397 m River Crossing, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9907 - Adana, Osmaniye and Erzurum Fuel Pipeline Variants
(Ministry of Defense, 1999-2000)
For 6,8 and 10 inch Pipelines (90 bar), 870 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9816 - Fuel Facilities Restoration (Year 1998)
(Ministry of Defense, 1998-2001)
For 4,6 and 8 inch Pipelines (90 bar), 2610 m Variant Construction, Hydrostatic Tests, Cathodic Protection Systems and Various Restoration Works at 13 Tank Farm and Pump Station Detailed Engineering and Construction Supervision
9815 - Denizli Cardak Rail Car Towing System and Osmaniye Manifold Station Restoration
(Ministry of Defense, 1998-2000)
Rail Car Towing System at Denizli Cardak Rail Unloading Point, 6 inch 70 m Pipeline, Cathodic Protection System and Osmaniye Low Pressure Manifold Station Detailed Engineering and Construction Supervision
9814 - Istanbul Alibeykoy and Izmit Tank Farms Restoration
(Ministry of Defense, 1998-2000)
Storm Water Drainage System at Alibeykoy Tank Farm, 1716 m Internal Road at Izmit Tank Farm Detailed Engineering and Construction Supervision
9808 - East Turkey Fuel Facilities Restoration (Year 1997)
(Ministry of Defense, 1998-2000)
Restoration of Pump Stations at North Iskenderun, Elazig, Adana, Mersin Tank Farms and Gezin Pump Station Detailed Engineering and Construction Supervision
9805 - Bursa, Karacabey and Sogut Fuel Pipeline Variants
(Ministry of Defense, 1998-2000)
For 4 and 6 inch Pipelines (90 bar), 245 m Road Crossing, 1610 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9801 - Esenyurt, Sazlidere, Yenicekoy and Erzin Pipeline Variants
(Ministry of Defense, 1998-2000)
For 4,6 and 8 inch Pipelines (90 bar), 120 m Road Crossing, 970 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9721 - Kemah, Sivas, Diyarbakır and Batman Pipeline Variants
(Ministry of Defense, 1997-1999)
For 4 and 8 inch Pipelines (90 bar), 100 m Road Crossing, 1875 m Variant Construction, 225 m Concrete Encasement, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9712 - Various Fuel Facilities Restoration (Year 1996)
(Ministry of Defense, 1997-1999)
For 4,6 and 8 inch Pipelines (90 bar), 2000 m Variant Construction, Hydrostatic Tests, Cathodic Protection Systems and Various Restoration Works at 11 Tank Farm Detailed Engineering and Construction Supervision
9709 - Istanbul Alibeykoy and Bursa Mudanya Fuel Pipeline Variants
(Ministry of Defense, 1997-1999)
For 4 and 6 inch Pipelines (90 bar), 225 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9708 - Sivas Divrigi Mursal Fuel Pipeline Variant
(Ministry of Defense, 1997-1998)
For 6 inch Fuel Pipeline (90 bar), 2319 m Variant Construction, Hydrostatic Test and Cathodic Protection System Detailed Engineering and Construction Supervision
9707 - West Anatolia Turkey Fuel Pipeline Variants (Year 1996)
(Ministry of Defense, 1997-1998)
For 4,6 and 8 inch Pipelines (90 bar), 890 m Variant Construction, 75 m Gabion Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9702 - East Turkey Fuel Pipeline Variants (Year 1996)
(Ministry of Defense, 1997-1999)
For 6 and 8 inch Pipelines (90 bar), 340 m River Crossing, 555 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9701 - Iskenderun Sariseki Fuel Pipeline Variants
(Ministry of Defense, 1997-1998)
For 3 each 8 inch and 1 each 24 inch Pipeline (90 bar), 5940 m Variant Construction, 40 m Road Crossing with Casing, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9601 - East Turkey Fuel Pipeline Variants (Year 1995)
(Ministry of Defense, 1996)
For 4,6 and 8 inch Pipelines (90 bar), 220 m River Crossing, 390 m Variant Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9504 - East Turkey Fuel Pipeline Variants (Year 1994)
(Ministry of Defense, 1995-1996)
For 4,6 and 8 inch Pipelines (90 bar), 155 m River Crossing, 1300 m Variant Construction, 20 m Gabion Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9503 - Fuel Facilities Restoration (Year 1995)
(Ministry of Defense, 1995-1996)
Various Restoration Works at Eskisehir and Erzurum Pump Stations Detailed Engineering and Construction Supervision
9304 - East Turkey Fuel Pipeline Variants (Year 1992)
(Ministry of Defense, 1993-1995)
For 4,6,8 and 10 inch Pipelines (90 bar), 1085 m River Crossing, 3420 m Variant Construction, 395 m Gabion Construction, 210 m Retaining Wall Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9203 - East and West Turkey Fuel Pipeline Variants (Year 1991)
(Ministry of Defense, 1992-1994)
For 4,6 and 8 inch Pipelines (90 bar), 550 m River Crossing, 4555 m Variant Construction, 270 m Gabion Construction, Hydrostatic Tests and Cathodic Protection Systems Detailed Engineering and Construction Supervision
9003 - Fuel Facilities Restoration (Year 1990)
(Ministry of Defense, 1990-1992)
Restoration of 7 each 1,250 cum Fuel Storage Tandk at 7 Tank Farm, Concrete Pavement Construction at 4 Pump Station Detailed Engineering and Construction Supervision
8102 - Restoration of Jet Fuel Facilies at Bandırma Main Airforce Base
(Ministry of Defense, 1981-1985)
Restoration of Jet Fuel Storage Tanks and Manifold System Detailed Engineering and Construction Supervision
8003 - Iskenderun Fuel Facilities Restoration
(Ministry of Defense, 1980-1984)
Restoration of Fuel Tanks Detailed Engineering and Construction Supervision
Services Provided By ESER
Detailed Engineering
Cost Estimations
Tender Documentation
Environmental Impact Study
Geophysical Studies
Geotechnical Studies
Basic Engineering
Topographical Surveys